Flow-Diagram Completion Exercise for Civil QC/QA Quality Planning
Purpose of Task
The purpose of this task is to enable learners to understand, visualize, and sequence key QA/QC processes in civil engineering projects using a flow-diagram format. By completing this exercise, learners will
- Learn to organize QA/QC activities visually, enhancing clarity and comprehension.
- Understand how inspection, reporting, escalation, and corrective action are linked systematically.
- Apply UK legislation, standards, and regulations in practical QA/QC workflows.
- Develop skills to communicate QA/QC processes clearly to project stakeholders.
- Ensure accountability, traceability, and compliance in project quality planning and documentation.
Scenario / Context
You are appointed as the QA/QC Officer for a high-rise residential project in London, UK. Your responsibilities include:
- Conducting inspections of materials and workmanship
- Preparing and maintaining quality documentation such as inspection reports, checklists, and NCRs (Non-Conformance Reports)
- Reporting and escalating non-conformances
- Ensuring compliance with UK standards and regulations
A recent internal audit revealed delays in reporting non-conformances, inconsistent escalation procedures, and lack of traceability in corrective actions. The project management team has requested a flow-diagram showing the complete QA/QC workflow, demonstrating how inspections, reporting, and escalation processes interconnect, while complying with UK legislation and standards.
Relevant UK Legislation and Standards:
- BS EN ISO 9001:2015 – Quality management systems
- Construction (Design and Management) Regulations 2015 (CDM 2015)
- Health and Safety at Work Act 1974 (HSWA 1974)
- Building Regulations 2010 – Structural integrity, fire safety, finishing standards
- BS EN 206 – Concrete specification, production, and conformity
- BS 5950 / Eurocode 3 & 4 – Structural steel design and quality
- CDM Approved Codes of Practice (ACoP)
Flow-Diagram Elements – Detailed Guidance
The flow-diagram should include the following process steps, showing clear sequencing and decision points:
Pre-Inspection Planning
- Activities: Prepare inspection checklists, review project specifications, assess potential risks
- Compliance: Align with BS EN ISO 9001:2015 Clause 8, CDM 2015 for safe work planning
- Stakeholders Involved: QA Officer, Site Supervisor
Site Inspection / Quality Check
- Activities: Inspect materials, workmanship, and conformance with design requirements
- Documentation: Record observations in inspection reports or checklists
- Compliance: Reference Building Regulations 2010, BS EN 206
- Stakeholders Involved: QA Officer, Site Engineer
Identification of Non-Conformance / Issues
- Activities: Compare inspection results with project specifications and UK standards
- Risk Classification: Minor, Major, Critical
- Compliance: ISO 9001:2015 Clause 10 – Nonconformity and Corrective Action
- Stakeholders Involved: QA Officer, Site Supervisor
Documentation & Reporting
- Activities: Complete inspection reports and NCRs, include details such as location, issue description, references to standards, date, and personnel
- Compliance: ISO 9001:2015 documentation requirements
- Stakeholders Involved: QA Officer, Project Manager
Escalation of Non-Conformance
- Activities: For major or critical issues, escalate to Project Manager, QA Manager, or Design Engineer
- Timelines: Define action deadlines based on severity
- Compliance: CDM 2015 Regulation 12 (coordination and communication responsibilities)
- Stakeholders Involved: QA Officer, Project Manager, Contractors
Corrective / Preventive Action Implementation
- Activities: Rework, retesting, additional supervision, or procedural adjustments
- Documentation: Record actions taken, update NCRs or inspection reports
- Compliance: ISO 9001:2015 Clause 10 – Corrective Action
- Stakeholders Involved: QA Officer, Site Engineer, Contractor
Verification / Closure
- Activities: QA Officer confirms the issue has been resolved and all actions implemented
- Documentation: Update NCR/inspection report status to “Closed”
- Compliance: ISO 9001:2015 Clause 10 – Effectiveness Verification
- Stakeholders Involved: QA Officer, Project Manager
Continuous Improvement / Lessons Learned
- Activities: Review inspection reports and NCRs, identify recurring issues, update quality plans and checklists
- Compliance: ISO 9001:2015 Clause 9 – Performance Evaluation / Improvement
- Stakeholders Involved: QA Manager, Project Management Team
Learner Task
Learners are required to:
- Complete the flow-diagram for the QA/QC process of a civil engineering project, covering all steps:
- Pre-inspection planning
- Site inspection / quality check
- Identification of non-conformance
- Documentation & reporting
- Escalation
- Corrective / preventive action
- Verification / closure
- Continuous improvement / lessons learned
- Include references to UK legislation and standards for each step,demonstrating regulatory compliance.
- Provide realistic examples of tasks, documents, and stakeholders for each process step.
- Include decision points for minor, major, or critical non-conformances.
- Submit a 2–3 page narrative explanation alongside the flow-diagram describing:
- How the workflow ensures compliance with UK legislation and standards.
- How escalation and documentation improve accountability and traceability.
- How the flow-diagram supports risk mitigation, project success, and continuous improvement.
Expected Learner Outcomes
Upon completing this task, learners will be able to:
- Visualize QA/QC processes in a civil engineering project using a flow-diagram.
- Apply systematic inspection, reporting, escalation, and corrective action procedures.
- Demonstrate understanding of UK legislation and standards in practical workflows.
- Identify and track non-conformances effectively, ensuring proper documentation and closure.
- Integrate continuous improvement principles into quality planning and documentation.
- Communicate QA/QC processes clearly and effectively to project stakeholders.